The preassembled panels are laid directly to the formwork of concrete slab.
The pipes are located only 5-8mm above the ceiling level. Due to the panel structure the system has outstanding heating and cooling capacity, quick reaction time and individual temperature control by rooms. The skin activation system is not core activation! Due to the lack of onsite installation, plastering and other phases the system provides the fastest installation, be it a small house or tens of thousands square meter residential building, hospital or office building.
New built residential, public or office buildings
The preassembled panels need to place directly to the formwork
The connection pipe’s end must to connect into a dedicated ducting element
First reinforcement layer can be installed directly to the panels
Do not need to make pressure test before pouring concrete
The panels must to connect in Tichelman principle in or outside of the slab.
Keep away any high temperature machines , cigarettes to prevent the pipe damages
The quality of the concrete should be checked by the architects
Pipe: 12mmx1,5mm PeRT
Pipe pitch distance : 90mm or 100mm
Maximum pressure loss: 30 kPa